Actemium Oil & Gas Commissioning

 

MAFUMEIRA SUL

Client: DSME  

End User: CHEVRON

Project Location: South Korea and Offshore Angola

Overall schedule: Started in 2013

  • Precommissioning and Commissioning engineering

    • Breakdown and definition of 998 Subsystems using MarkupTools
    • Preparation and redaction of 285 functional tests procedures
    • Database completion with around 63,000 tasks of Pre-Commissioning and Commissioning
  • Management of Commissioning execution at Yard (South Korea) and offshore (Angola)

  • Preparation of project general procedures
    (Master Systems Register, Commissioning sequence, PunchList Control Procedure, Commissioning HES Plan, Software Change control procedure etc)

Mafumeira Field is located in Block 0, approximately 24km offshore Cabinda province, Angola, at a water depth of 60m. Mafumeira Ful project is the second phase of the development of the field. The project is estimated to reach 110,000 barrels of crude oil and 10,000 barrels of liquefied petroleum gas. It includes a central processing facility, two wellhead platforms and a living quarter platform. 